Documents

Inframark WTP Report

View original document →

Ebensburg Municipal Authority: May 2025 WTP Monthly Report

Date: June 23rd, 2025 Submitted by: Luke Byrne, Inframark Water Infrastructure Operations

Executive Summary & Plant Operations

During May 2025, the Ebensburg water treatment plant treated a total of 36,835,000 gallons of reservoir water. This represents an average daily production of 1,188,226 gallons, which is a significant increase compared to the previous year.

  • Water Sourcing: An average of 63,854 gallons per day was purchased from Saltlick and blended into the distribution system.
  • Production Range: Daily plant production fluctuated between 1,097,000 and 1,317,000 gallons.
  • Reservoir Levels: The upper reservoir water level is currently at -1 ft and is rising due to recent precipitation.

Maintenance & Repairs

Inframark staff completed 65 work orders in May. Key activities included:

  • Equipment Servicing:
    • Hillcrest generator serviced (May 19th); found in good condition.
    • DAF permanganate pump taken offline for maintenance; injector valve cleaned and lines cleared.
    • DAF Recycle pump rebuilt.
    • Ogden vault pumped out due to groundwater infiltration.
  • Inspections & Cleaning:
    • Fire extinguisher and ladder inspections performed.
    • Clarifier troughs cleaned; grease applied to clarifier drives and finished water pumps/motors.
    • pH and turbidity meters cleaned weekly.
    • Facility swept and cleaned.
  • Repairs:
    • Two cable bolts replaced on the gas chlorine scale.
    • Chlorine scale bolt repair completed.
    • Two light bulbs replaced at Saltlick.

Compliance & Sampling

All samples collected in May were found to be in compliance with state regulations.

  • Bacteriological: Nine samples collected; zero total coliform positives.
  • Chemical: Annual sampling of inorganic (IOC), volatile organic (VOC), and synthetic organic compounds (SOC) completed.
  • Chlorine: Five samples collected in the distribution system; all met the minimum requirement of 0. 20mg/L free chlorine.
  • Lead and Copper: Sampling scheduled for upcoming months ("On the Radar").

Financial Update

Maintenance Expenditures:

  • eBay: $111. 40 (Indicator lights)
  • Lowes: $183. 29 (Screening unit cleaning project)
  • Ace Hardware: $23. 19 (Pressure washer fittings)

Budget Caps (WTP):

  • Maintenance Cap:
    • Contract Total: $25,950. 84
    • Spent This Month: $318. 60
    • Remaining Balance: $14,492. 25
  • Chemical Cap:
    • Contract Total: $93,423. 12
    • Spent This Month: $13,260. 25
    • Remaining Balance: $35,740. 53

Health & Safety

  • Accidents: None reported in May.
  • Safety Record: Personnel have worked 1,947 days (5 years, 5 months) without an accident or injury.
  • Training: Weekly tailgate meetings and PPE Program updates were conducted.

Personnel

The following staff members are certified for operations:

  • Kyle Smiley (Operator): PA Class A, E, Subclass 1, 10, 11, 12
  • Tony Perott (Operator): PA Class C, E, Water Subclass 1, 6, 7, 8, 12
  • Cody Williams (Operator in Training): Training for PA DEP exam
  • Shawn Jones (Operator in Training): Training for PA DEP exam
  • Luke Byrne (Project Manager): PA Class A, E, Water Subclass 1, 7, 8, 10, 11, 12; PA Class A, E, Wastewater

Upcoming Items ("On the Radar")

  • DAF Spare parts
  • Upper reservoir gate valves
  • Online pH probe replacement
  • Lead and Copper sampling
← Back to Documents