Inframark WTP Report
View original document →
Ebensburg Municipal Authority: May 2025 WTP Monthly Report
Date: June 23rd, 2025 Submitted by: Luke Byrne, Inframark Water Infrastructure Operations
Executive Summary & Plant Operations
During May 2025, the Ebensburg water treatment plant treated a total of 36,835,000 gallons of reservoir water. This represents an average daily production of 1,188,226 gallons, which is a significant increase compared to the previous year.
- Water Sourcing: An average of 63,854 gallons per day was purchased from Saltlick and blended into the distribution system.
- Production Range: Daily plant production fluctuated between 1,097,000 and 1,317,000 gallons.
- Reservoir Levels: The upper reservoir water level is currently at -1 ft and is rising due to recent precipitation.
Maintenance & Repairs
Inframark staff completed 65 work orders in May. Key activities included:
- Equipment Servicing:
- Hillcrest generator serviced (May 19th); found in good condition.
- DAF permanganate pump taken offline for maintenance; injector valve cleaned and lines cleared.
- DAF Recycle pump rebuilt.
- Ogden vault pumped out due to groundwater infiltration.
- Inspections & Cleaning:
- Fire extinguisher and ladder inspections performed.
- Clarifier troughs cleaned; grease applied to clarifier drives and finished water pumps/motors.
- pH and turbidity meters cleaned weekly.
- Facility swept and cleaned.
- Repairs:
- Two cable bolts replaced on the gas chlorine scale.
- Chlorine scale bolt repair completed.
- Two light bulbs replaced at Saltlick.
Compliance & Sampling
All samples collected in May were found to be in compliance with state regulations.
- Bacteriological: Nine samples collected; zero total coliform positives.
- Chemical: Annual sampling of inorganic (IOC), volatile organic (VOC), and synthetic organic compounds (SOC) completed.
- Chlorine: Five samples collected in the distribution system; all met the minimum requirement of 0. 20mg/L free chlorine.
- Lead and Copper: Sampling scheduled for upcoming months ("On the Radar").
Financial Update
Maintenance Expenditures:
- eBay: $111. 40 (Indicator lights)
- Lowes: $183. 29 (Screening unit cleaning project)
- Ace Hardware: $23. 19 (Pressure washer fittings)
Budget Caps (WTP):
- Maintenance Cap:
- Contract Total: $25,950. 84
- Spent This Month: $318. 60
- Remaining Balance: $14,492. 25
- Chemical Cap:
- Contract Total: $93,423. 12
- Spent This Month: $13,260. 25
- Remaining Balance: $35,740. 53
Health & Safety
- Accidents: None reported in May.
- Safety Record: Personnel have worked 1,947 days (5 years, 5 months) without an accident or injury.
- Training: Weekly tailgate meetings and PPE Program updates were conducted.
Personnel
The following staff members are certified for operations:
- Kyle Smiley (Operator): PA Class A, E, Subclass 1, 10, 11, 12
- Tony Perott (Operator): PA Class C, E, Water Subclass 1, 6, 7, 8, 12
- Cody Williams (Operator in Training): Training for PA DEP exam
- Shawn Jones (Operator in Training): Training for PA DEP exam
- Luke Byrne (Project Manager): PA Class A, E, Water Subclass 1, 7, 8, 10, 11, 12; PA Class A, E, Wastewater
Upcoming Items ("On the Radar")
- DAF Spare parts
- Upper reservoir gate valves
- Online pH probe replacement
- Lead and Copper sampling