Inframark WWTP Report

View original document →

Executive Summary

Inframark submitted the June 2026 monthly report for the Ebensburg wastewater treatment facility. Key operational highlights include:

  • Volume: The plant treated 29,253,000 gallons of wastewater (averaging 641. 76 gallons per day).
  • Sludge: The centrifuge was operated weekly, sending 10. 94 tons of dry sludge to the landfill.
  • Maintenance:
    • Replaced a faulty exhaust fan motor in the headworks building.
    • Installed new conduit and an electric solenoid for automated wash cycles on the screening unit.
    • Repaired the effluent sample fridge by replacing the power supply and thermostats.
    • Addressed overheating issues in the blower building (caused by warm weather) that led to a decanter failure on #4 SBR.
    • Corrected wet end bearing temperature issues on the centrifuge.
  • Grounds: Repaired lawns and re-planted process water tank excavations.

Financial Caps

The following table outlines the budget status for the current contract year:

Category Contract Total per Year Previous Balance Total Spent this Month Remaining Balance
Maintenance Cap $26,664. 12 $17,767. 81 $3,783. 76 $13,984. 05
Sludge Cap $85,325. 04 $57,492. 66 $7,271. 78 $50,220. 88
Chemical Cap $23,890. 92 $15,358. 92 $2,808. 00 $12,550. 92

Health & Safety

  • Accidents: There were no accidents in June.
  • Safety Record: Personnel have worked 2,342 days (6 years and 6 months) without an accident or injury.
  • Training: Staff participated in weekly tailgate meetings, safety flash reports, and process control meetings.

Upcoming Items ("On the Radar")

  • SCADA programming
  • Lawn repairs
  • Influent splitter box lid repair
  • SBR #2 air valve
  • UV ballast wire

Personnel

The following staff members are listed with their titles and certifications:

  • Randy Lauer (Operator II): PA Class A, E; Wastewater Subclass 1,2,3,4
  • Kyle Smiley (Operator III): PA Class A, E; Water Subclass 1,10,11,12; Wastewater Subclass 1
  • Tony Perott (Operator I): PA Class C, E; Water Subclass 1,6,7,8,12
  • Shawn Jones (Mechanic II): NA
  • Joseph Pompa (Operator in Training): Training for PA DEP exam
  • Joseph Blythe (Operator in Training): Training for PA DEP exam
  • Luke Byrne (Project Manager): PA Class A, E; Water Subclass 1,7,8,10,11,12; Wastewater Subclass 1,3,4