Inframark C&D Report
View original document →
Executive Summary of June Operations
Inframark submitted this monthly report for the Ebensburg Municipal Authority regarding water collection and distribution operations for June 2026. Key operational updates include:
- Leak Detection and Repair: Staff performed regular leak detection using listening equipment. On June 2nd, repairs were completed on Beech Street involving a leaking air release valve and a broken 4-inch main. New leaks were discovered on Margaret Street and Charles Street, alongside errors in the GIS pipe documentation which are currently being corrected.
- Pumping Stations: Drinking water pumping stations were inspected regularly, including greasing pumps/motors and inspecting packing glands. The Ogden tank was checked for leaks, and weekly sampling/calibrations were completed. Two power outages occurred at the Ogden pumpstation, but all stations were swept and cleaned.
- Sewer Lift Stations: Regular inspections occurred, including generator checks and wet well pumping. No leaks were found in flanges or seats, and basket screeners were cleaned out.
Upcoming Maintenance ("On the Radar")
The following repairs and investigations are scheduled or pending:
- Highland Avenue leak (pending state permits)
- WTP Manor Drive Line leak
- West Street service line leak
- Sample Street leak investigation
- Margaret Street leak
- Charles Street leak
- Hillcrest Pressure test
- Emerald Estates check valve repairs
Financial Update
The report details maintenance expenditures and budget caps for the Water Treatment Plant (WTP).
Maintenance Expenditures
- Home Depot: $136. 74 (Trimmer for hydrants)
- Ace Hardware: $69. 86 (Epoxy glue/electrical connectors)
WTP Maintenance Cap Status
- Contract Total per Year: $5,000. 00
- Previous Balance: $3,097. 12
- Total Spent This Month: $206. 60
- Remaining Balance: $2,890. 52